ZTC logo
School Extension

Latvia • Developer project

School Extension

Developer
School Extension image 1

About this project

By designing for industrial production from the outset, ZTC maximised panel sizes and factory completion levels. Structural elements were manufactured in parallel with on-site foundation works. Panels were delivered and installed directly from the truck, eliminating site storage and optimising crane time. While ZTC crews assembled the third building, interior works were already underway in the first, achieving a significantly shorter overall construction cycle.

Specifications

Area
3000 m²
Floors
2
Year completed
2020
Building type
Developer project

Planning a similar project?

Explore the relevant construction system and project process. To discuss a proposal, send your plans and sections, approximate floor area, construction country and the work you would like ZTC to undertake. If you do not have drawings yet, describe your idea. Package scope, delivery, assembly and timing are agreed for each project.

Discuss your project